How many business days do you have, state by state?
Every state and territory has a security of payment law. When you receive a payment claim, the Act sets the time in which you must answer it with a payment schedule (in the Northern Territory, a notice of dispute), or earlier if your contract says so. This is general information, not legal advice: the Acts change, and the facts of a contract matter. Check the Act and ask your lawyer before relying on a deadline.
| Where | Time to give a payment schedule | If you miss it |
|---|---|---|
| NSW | 10 business days | Liable for the full amount claimed, without contract defences or cross-claims if the claimant goes to adjudication or court (NSW Government) |
| Victoria | 10 business days | Liable for the full amount claimed, and no adjudication response (Building and Plumbing Commission) |
| Queensland | 15 business days | Liable for the amount claimed on the due date; failing to give a schedule also carries a maximum penalty of 100 penalty units (BIF Act, ss 76 and 77) |
| Western Australia | 15 business days, for contracts entered into from 1 August 2022 | The government’s guide says “serious consequences may follow” (WA Government) |
| South Australia | 15 business days | Liable for the claimed amount on the due date (SA Act, s 14) |
| ACT | 10 business days | Liable for the claimed amount (ACT Act, s 16) |
| Tasmania | 10 business days; 20 where the claim is for a home, the respondent owns the land and is not a building practitioner | Liable for the claimed amount (Tas Act, s 19) |
| Northern Territory | No payment schedule. Where the contract is silent, give a notice of dispute within 10 working days, or pay the whole claim within 20 working days | No deemed liability; a payment dispute goes to adjudication (NT Act, Sch 1) |
A contract cannot stretch these times: outside the NT, the deadline is the Act’s or the contract’s, whichever is earlier. In Victoria, since 15 April 2026, “business day” excludes 22 December to 10 January (Building and Plumbing Commission).
How do you make sure you never miss one?
The deadline runs from when the claim reaches you, not from when it reaches accounts. A common cause of a missed schedule is a claim that sat in a project manager’s inbox. A process that works:
- One address for claims. Put it in every subcontract, and forward anything that lands elsewhere the same day.
- Date-stamp on arrival. Record the date received and work out the schedule deadline at once, in business days for that state.
- Keep a register. Claim, subcontractor, project, amount, date received, schedule due, who decides, status. Review it daily.
- Send it to the person who can assess it, with the date. The project manager checks the work done against the claim.
- Write the schedule early. State the amount you propose to pay and every reason for paying less. In Victoria, since 15 April 2026, reasons not raised in the schedule cannot be brought up later in an adjudication response.
- Serve it, and keep proof. Send it the way the contract and the Act allow, and file the evidence of when.
A NSW claim received on Friday 13 November 2026
- Business days 1 to 5
- Mon 16 to Fri 20 Nov
- Business days 6 to 10
- Mon 23 to Fri 27 Nov
- Last day for the payment schedule
- Fri 27 Nov
Counting excludes weekends and public holidays. Confirm how your state’s Act defines a business day, and whether the contract sets an earlier date.
How long can you take to pay?
The Acts also cap payment terms, so a contract cannot push payment out indefinitely.
| Where | Maximum time to pay after a claim |
|---|---|
| NSW | 20 business days for a subcontractor (excluding exempt residential work); 10 for a subcontractor on exempt residential work; 15 for a head contractor claiming from the principal (NSW Government) |
| Queensland | 25 business days for subcontracts; 15 for commercial building contracts; a longer term is void and a 10-business-day default applies (QBCC) |
| Victoria | 20 business days, since 15 April 2026 |
| Northern Territory | A term requiring payment more than 30 working days after a claim is read as 30 working days |
Victoria’s 2026 reforms also removed “excluded amounts” and “claimable variations”, replaced reference dates with a monthly entitlement to claim, and apply to contracts made before 15 April 2026 as well (Building and Plumbing Commission).
What does a NSW head contractor have to declare?
In NSW, a head contractor’s payment claim to the principal must include a supporting statement, on the approved form, declaring that all subcontractors have been paid, and noting any amounts in dispute. The NSW FAQ gives a maximum penalty of A$22,000 for failing to provide one, and false or misleading statements can also bring imprisonment (NSW FAQ). A later NSW page puts the maximum for a corporation higher, at A$110,000 (NSW, changes to the laws). Either way, the statement is only as good as your record of what each subcontractor has been paid.
Do you have to hold retentions in trust?
It depends on the state and the size of the contract.
- NSW: retention money must be held in a trust account where the contract is worth A$20 million or more, and Building Commission NSW notified within 10 business days of opening it (NSW FAQ).
- Western Australia: a retention trust scheme applies to new eligible contracts over A$20,000 including GST, since 1 February 2024 (WA Government).
- Queensland: project and retention trust accounts began on 1 March 2021. On 10 February 2025 the rollout to private projects under A$10 million was paused; they still apply to eligible Queensland Government contracts of A$1 million or more and other contracts of A$10 million or more (QBCC).
How do you record retentions in MYOB AccountRight?
MYOB’s help describes a method rather than a dedicated feature (MYOB, Withholding payments from contractors):
- Create an Other Liability account, Retentions Payable.
- Create a Retainer Withheld item you buy, linked to that account.
- Enter each progress bill on the Item layout with the retention as a negative line.
- Use the Purchases (Item Summary) report to see what is held.
- On the final bill, add the retention back as a positive line, which clears the account.
The method has no release dates or reminders, so keep a schedule of when each retention falls due.
What else applies to subcontractor bills?
- TPAR. Businesses in building and construction that pay contractors for those services may need to report the payments in a Taxable payments annual report, due by 28 August each year (ATO).
- Recipient-created tax invoices. If you issue the invoices for your subcontractors, both parties must be registered for GST, a written agreement must be in place, the ATO’s determination must cover the kind of supply, and you must give the supplier the RCTI within 28 days (ATO, Tax invoices).
Where Docket AP fits
Docket AP reads a subcontractor’s invoice like any bill, checks it, shows its due date in words, and sends it to the project manager the rules name. An approver who has not answered is reminded after two working days, which is built and paused until real email is switched on. It does not recognise a document as a payment claim, count business days for a payment schedule, draft schedules or keep a retention ledger. Keep your claims register for that.
Questions people also ask
Does the deadline run from when the claim was received or when it was dated?
From when the payment claim was served on, or given to, you, depending on the Act. That is why a claim should be date-stamped the day it arrives, wherever it arrives, and not when it reaches accounts.
Can a contract give me longer than the Act to reply?
No. Under every state and territory Act listed here except the Northern Territory’s, the contract can only shorten the time: the deadline is the Act’s or the contract’s, whichever is earlier.
Do the deadlines count weekends and public holidays?
No. The state Acts count business days, which leave out weekends and public holidays, and Victoria now leaves out 22 December to 10 January; check your own Act’s definition, as others exclude days over Christmas too. The Northern Territory counts working days. Check each Act’s definition before you count.
Does MYOB AccountRight track retentions?
MYOB’s help describes a method rather than a feature. Create a Retentions Payable liability account and a Retainer Withheld item, enter the retention as a negative line on each progress bill, and add it back as a positive line on the final bill.
Do retention trusts apply in every state?
No. In NSW a trust account is needed only for contracts of A$20 million or more; Western Australia’s scheme covers eligible contracts over A$20,000; Queensland’s applies to government contracts of A$1 million or more and other contracts of A$10 million or more. Check the rules for your contract.
Sources
Each one read at source on the date shown. Quotes are kept short; follow the link for the full text.
- Responding to a payment claim
- Making a payment claim
- Security of payment, frequently asked questions
- Changes to the security of payment laws
- Responding to a payment claim under the SOP Act
- Changes to the SOP Act
- Building Industry Fairness (Security of Payment) Act 2017
- Request payment
- Pausing the further rollout of trust accounts
- Responding to a payment claim
- Cook Government completes reforms on subcontractor payments
- Building and Construction Industry Security of Payment Act 2009 (SA)
- Building and Construction Industry (Security of Payment) Act 2009 (ACT)
- Building and Construction Industry Security of Payment Act 2009 (Tas)
- Construction Contracts (Security of Payments) Act 2004 (NT)
- Withholding payments from contractors
- Work out if you need to lodge a TPAR
- Tax invoices